A PTFE filter bag is ready for installation only when the bag, cage, tube-sheet opening, top seal, bottom construction and available clearance have been checked as one assembly. Nominal bag diameter and length alone cannot establish fit. Record the drawing datums and measurement condition, verify the actual hardware, install without forcing or scraping the media, and preserve a signed row-by-row inspection record before commissioning.
This guide is a project-specific acceptance worksheet, not a universal dimensional standard. It supplies no generic bag-to-cage clearance, snap-band size, length tolerance, commissioning limit or operating set point. Use the collector manufacturer’s approved drawing and instructions, the bag supplier’s order documents, and the plant’s authorized isolation and start-up procedures.
Freeze the assembly definition before measuring
Identify the collector, compartment, row and position; bag and cage drawing numbers and revisions; bag lot; cage type; tube-sheet drawing; cleaning system; installation orientation; and any venturi or support hardware. Mark each value as drawing, purchase record, direct measurement or unresolved assumption. A sample removed from service can reveal construction details, but wear, shrinkage, permanent set and previous repair can make it an unreliable dimensional master.
The existing PTFE filter bag selection guide addresses media and duty selection. The failure guide addresses damage already found in service, while the replacement-trial guide addresses operating comparisons. This page owns the installation interface and pre-start acceptance record.
Measure bag and cage from named datums
State how bag diameter or circumference is measured, whether the textile is relaxed, and where the length begins and ends. For the cage, record outside envelope, total supported length, vertical-wire arrangement, ring spacing, joints, top style, venturi and bottom pan. Inspect for bent wires, high welds, corrosion, sharp edges, loose joints and distortion. Do not accept a cage merely because it enters the bag.
Compare the two components through the approved drawing or supplier fit definition. The bag must be supported as intended without harmful folds, forced stretching, spiraling or concentrated rubbing. The required relationship depends on construction and collector design; copying a clearance from another baghouse can convert a useful check into an incorrect requirement.
Match the cuff to the tube sheet and cage top
Identify the top construction exactly: for example, a snap band, flange, raw edge with clamp, cuff, loop or another drawing-defined arrangement. Record tube-sheet hole geometry, thickness, edge condition, corrosion, flatness and any gasket groove or support feature. Also record the cage-top and venturi arrangement because the top seal and cage support interact.
For one specific snap-band product system, Parker instructs installers to protect the bag surface with an installation sleeve, seat the tube sheet in the band groove, confirm that the expanded band is round and secure, and lower the cage straight rather than dropping it. These are useful examples of controlled checks, not universal instructions for every cuff. Donaldson’s LP collector manual likewise shows a model-specific sequence in which the bag collar captures the tube sheet before the cage is lowered. Follow the instructions for the actual collector and supplied construction.
Verify bottom construction and installation clearance
Record whether the bottom is a disc, cap, reinforced panel, loop, thimble connection or another specified form. Check the seam transition, reinforcement height, cage-end shape and required relationship between the cage end and bag bottom. Confirm that joints or projections cannot create a local contact point. Never invent a bottom allowance by subtracting catalog dimensions that use different datums.
Use the collector drawing and a physical inspection to confirm clearance to the hopper, housing, baffles, inlet zone, adjacent bags and any internal obstruction throughout the installed path. Check access above the tube sheet for controlled insertion of the bag and cage. “It can be pushed in” is not acceptance: forcing a cage can scrape a membrane, spiral the bag, deform the cuff or conceal an obstruction. Parker’s installation instructions explicitly caution against dropping or forcing cages in the referenced systems.
Use a drawing-linked fit worksheet
Complete the record with units, datums, method, sample size and instrument identification. Enter the approved requirement and the observation separately; do not average conflicting sources or fill blanks from a generic catalogue.
| Interface field | Approved requirement / source | Observed result | Disposition |
|---|---|---|---|
| Bag diameter or circumference; condition | ___ | ___ | ___ |
| Bag length and end datums | ___ | ___ | ___ |
| Cage outside envelope and supported length | ___ | ___ | ___ |
| Cage wires, rings, joints, welds and bottom | ___ | ___ | ___ |
| Tube-sheet opening, thickness and edge | ___ | ___ | ___ |
| Cuff, seal, cage top and venturi | ___ | ___ | ___ |
| Bag bottom and reinforcement | ___ | ___ | ___ |
| Installed clearances and access path | ___ | ___ | ___ |
Inspect every installed position before closing the collector
Protect the clean side and bag surface from debris and sharp contact. Use the approved handling method and installation aids. After placement, verify that the top seal is completely seated, the cage is fully supported, the bag is not twisted or pinched, seams have the specified orientation, and no tool, packaging or foreign material remains. Map damaged or questionable positions instead of silently replacing them.
Perform any seal, grounding, tension or rotation check only when required by the actual design. In Donaldson’s cited collector, the final check includes smooth rotation of the cleaning arms; this does not apply to collectors without that mechanism. Record who inspected each position, the result, any nonconformance, corrective action and reinspection.
| Check | Position / evidence | Result | Reviewer |
|---|---|---|---|
| Top seal fully seated and undamaged | ___ | ___ | ___ |
| Cage seated; no force, twist or pinch evident | ___ | ___ | ___ |
| Bottom and adjacent clearances confirmed | ___ | ___ | ___ |
| Clean side and compartment free of debris | ___ | ___ | ___ |
| Required hardware, controls and monitors checked | ___ | ___ | ___ |
| Nonconformances closed and reinspected | ___ | ___ | ___ |
Commission against a documented plant baseline
The US EPA inspection manual recommends a pre-start check of bag security, seals, controls, fan direction and other system items, while emphasizing that general guidance supplements rather than replaces the manufacturer’s manual for the particular baghouse. Build the commissioning record around the plant’s approved procedure: equipment status, airflow or fan state, temperature and moisture, differential pressure with tap locations, cleaning-system status, outlet particulate indicator or leak detector, and observed leaks or abnormal noise.
New media may begin with a different resistance and conditioning state from used bags. Capture time-aligned baseline trends and cleaning events rather than declaring success from one reading. Use site-approved limits; an outlet alarm, abnormal pressure, loss of capture, condensation risk or mechanical concern triggers the plant’s authorized response. This worksheet does not define a legal emissions test, a performance guarantee or a universal seasoning procedure.
Release the installation with traceable evidence
The release package should contain approved drawings, lot and position map, fit measurements, installation checklist, nonconformance closure, photographs where permitted, instrument status and initial operating trends. Preserve unresolved deviations for engineering disposition. A signed installation record establishes what was checked; it does not prove future service life or suitability outside the reviewed duty.
For an order-specific review, send the approved bag, cage and tube-sheet drawings, top and bottom details, installation access constraints and required documents with your inquiry for custom PTFE filter bags. Availability, tolerances, inspection scope and compatibility require written confirmation for the project.
Prepare a Drawing-Based PTFE Filter Bag Fit Review
Frequently asked questions
What clearance should a PTFE filter bag have over its cage?
There is no universal clearance in this guide. Use the approved bag-and-cage fit definition for the specific textile construction, cage and cleaning system, including measurement condition and datums.
Can an old bag be used to set replacement length?
It can supply evidence, but wear, shrinkage, stretch, deposits and previous installation can alter it. Reconcile the sample with controlled drawings, cage and tube-sheet geometry.
Does a cage that slides into the bag prove acceptance?
No. Acceptance also requires the correct support length, top and bottom relationship, seal, orientation, clearances and absence of harmful force, twist, folds or sharp contact.
What should be recorded after start-up?
Use the plant-approved procedure to record operating state, flow context, temperature and moisture, differential pressure, cleaning activity, outlet indication, leaks, alarms and corrective actions over a representative period.
Technical references
Ready to request a quote? Send your drawing or specifications, quantity, destination country and operating conditions for a project-specific review.