A replacement PTFE hose assembly needs a controlled interface package, not a resemblance check. Identify both end connections and their sealing features, define the finished-length datums, state elbow clocking from a named viewing direction, document the installed route and service conditions, and preserve the original equipment or approved drawing reference. Measurements from a removed hose are useful evidence, but they do not by themselves prove the original specification.
This guide is a blank engineering and RFQ workflow. It does not identify an unknown fitting from a photograph, prescribe a universal tolerance, or confirm that a proposed substitute is interchangeable. The equipment owner and responsible engineer must resolve missing requirements and approve any change before installation.
Start with identity and change control
Record the equipment tag, hose assembly tag, original manufacturer and part number, drawing number and revision, purchase record, and the reason for replacement. Photograph the layline and permanent tags before cleaning or removal if site procedures allow. Keep the removed item traceable to its installation position; two visually similar hoses on the same skid may have different duty, orientation or end details.
Search controlled records before reverse-measuring the old part. An approved drawing or original data sheet can reveal a sealing standard, material, electrical requirement or test scope that appearance cannot. Mark every data point by source: controlled document, legible marking, direct measurement, installed observation, or assumption requiring resolution.
If the replacement changes the liner, reinforcement, end design, material, routing or qualification basis, treat it as a proposed design change. The earlier hose quotation BOM checklist helps compare bids after the replacement definition is approved; it does not establish the definition.
Define each end by its sealing interface
Describe end A and end B separately. Record the connection family and standard or controlled drawing, nominal size, thread designation and pitch where applicable, male or female form, swivel or fixed construction, sealing location, sealing-face geometry, gasket or seal requirement, material, and any flange class or tube size needed by that interface. “One-inch thread” or “standard flange” is not a complete identification.
Use the applicable standard only for the feature it governs. ASME B1.20.1 covers dimensions and gaging for NPT, NPSC, NPTR, NPSM and NPSL pipe threads. It does not make those thread forms interchangeable or define the complete hose assembly. ASME B16.5 covers specified sizes and classes of pipe flanges and flanged fittings, including dimensions and tolerances; it is not a universal label for every flange or hose end. Record the actual designation and edition required by the owner.
Inspect the mating component as well as the removed end. A thread may provide retention while another surface provides the seal. Photograph the sealing face square-on with a scale, but do not infer thread form, material grade or pressure class from a photograph alone. Use appropriate gauges, controlled drawings or qualified inspection when identity is uncertain. The PTFE fittings and connections guide provides general connection context; this replacement record owns the exact interface evidence.
Dimension finished length from named datums
State what “length” means. Depending on the end, the relevant datum might be a sealing face, the end of a straight fitting, the centreline of an elbow seat, or another drawing reference. Parker’s official Parflex thermoplastic and fluoropolymer hose catalogue gives product-system examples in which overall length is measured to different references for straight and elbow fittings. That convention demonstrates why the datum must be explicit; it is not automatically the correct convention for another manufacturer’s assembly.
Record the finished datum-to-datum length, units, tolerance and measurement condition. Also record the flexible hose length when it matters to routing. Do not subtract generic fitting allowances or copy a nominal hose cut length unless the approved assembly system defines them. A finished assembly dimension and a loose-hose cut length are different controls.
Measure the removed assembly unloaded and in a stated condition, using a method that does not force it straight or damage it. Repeat the measurement and record uncertainty. A used hose may have taken a set, stretched, shortened, twisted, thermally changed, or been assembled to an earlier revision. It can corroborate the installation envelope; it cannot silently replace missing design records.
Specify elbow clocking without ambiguity
When both ends contain non-straight features, define their angular relationship. Choose and label the far end, state the viewing direction along the assembly, define the zero-degree reference, and state whether the angle increases clockwise or counter-clockwise. Provide a view or section that makes the end features visible, plus a tolerance approved for the installation.
The Parker Parflex catalogue defines one ordering convention for two elbows: select a far end and measure the near end clockwise. Use that only when the selected supplier’s assembly system accepts the same convention. Otherwise place the project-specific definition directly on the drawing. “Elbows aligned” and “90 degrees apart” are incomplete if the viewer and direction are absent.
For flanges, identify whether clocking refers to a bolt-hole pattern, a single hole, an elbow centre plane or another feature. For swivels, distinguish a freely adjustable installation position from a fixed crimped orientation. Never assume a swivel makes hose-body torsion acceptable.
Capture the installed route and service state
Photograph and sketch the hose in its normal installed position before removal. Show connection points, supports, guards, nearby hot or abrasive surfaces, movement envelope, gravity sag, minimum available clearance, and the bend planes. Record whether the equipment was depressurized, cold, stationary or at another defined state. Installation dimensions taken between ports should identify the equipment state and measurement references.
Swagelok’s official hose installation card says length selection must consider movement, system pressurization, thermal expansion and machine tolerances; it also calls for the specified minimum bend radius, sufficient straight length at fittings and bending in one plane to avoid twist. These are routing principles, not dimensional values for an unidentified hose. Obtain the proposed assembly’s own bend-radius and straight-length requirements.
Describe the service envelope: fluid identity and concentration, contamination or cleanliness needs, normal and upset temperature, internal and external pressure or vacuum, pressure transients, motion and cycle, vibration, electrical or static-control requirement, external exposure, regulatory or owner specification, and consequence of leakage. Do not approve a replacement from geometry alone.
Use a traceable replacement worksheet
Complete the evidence and requirement columns before requesting a quotation. Leave an item open when the source is uncertain. The supplier-response column should cite a drawing, technical data sheet or written exception rather than restating “equivalent.”
| Field | Existing evidence and source | Approved replacement requirement | Supplier response / exception |
|---|---|---|---|
| Identity and revision | Tag ___; drawing ___ Rev ___ | Controlled reference ___ | ___ |
| End A interface | Standard/drawing ___; size ___; seal ___ | Designation, material and datum ___ | ___ |
| End B interface | Standard/drawing ___; size ___; seal ___ | Designation, material and datum ___ | ___ |
| Finished and flexible length | Condition/method ___; value ___ | Datums, value and tolerance ___ | ___ |
| Elbow / flange clocking | View and measured angle ___ | View, zero, direction, angle, tolerance ___ | ___ |
| Liner, braid and cover | Marking/document/unknown ___ | Construction and materials ___ | ___ |
| Installed route | Photos/sketch/state ___ | Bend, straight length, supports, motion ___ | ___ |
| Service envelope | Operating record/specification ___ | Media, temperature, pressure/vacuum, motion ___ | ___ |
| Testing and documents | Original requirement/record ___ | Procedure, acceptance, traceability ___ | ___ |
| Open assumptions | Unknowns ___ | Resolution owner and evidence ___ | ___ |
Resolve conflicts instead of averaging them
Compare the controlled drawing, markings, measured old assembly and installed port geometry. If they disagree, preserve all observations and investigate the cause. Do not average two lengths, choose the most convenient thread gauge, or alter clocking so the old hose “looks right.” Check drawing revision, equipment modification history, adapter use, permanent deformation and measurement datum first.
| Finding | Do not assume | Required resolution |
|---|---|---|
| Marking is missing or unreadable | Construction or rating from appearance | Use records, qualified examination and supplier review; keep identity open |
| Old length differs from drawing | The drawing or old hose is automatically correct | Confirm revision, datum, condition and installed geometry with the owner |
| Thread starts but fit is uncertain | Thread engagement proves sealing compatibility | Verify designation, pitch, form, seal location and mating component |
| Two elbows appear aligned | Clocking is 0° without a view convention | Create a controlled view, zero reference, direction and tolerance |
| Proposed assembly fits between ports | Geometry proves service suitability | Review the complete construction, service envelope, routing and qualification |
Request written confirmation of supplier capability for the exact hose-and-end combination, dimensions, clocking, materials, service response, inspection and records. Catalogue examples from another product family cannot qualify the proposed assembly. Any deviation needs the designated engineer’s disposition before purchase or installation.
Frequently asked questions
Can a supplier copy the old hose from photographs?
Photographs help document layout and visible interfaces, but they cannot reliably establish hidden sealing geometry, thread designation, materials, condition-dependent length or service qualification. Supply controlled records and measurements, and identify unresolved fields.
Where should end-to-end length be measured?
Between the datum planes defined for the actual end connections. State the references on the drawing; do not assume that every end uses its physical tip.
Is elbow clocking needed if one end swivels?
It depends on which features remain fixed after installation. Document swivel function and final orientation requirements. A swivel does not authorize twisting the hose body.
Can a worn hose be used as the master?
Use it as one evidence source. Age, pressure, temperature, installation strain, damage and prior modifications can make its present shape different from the intended new condition.
Prepare a drawing-based replacement enquiry
Submit the completed worksheet, controlled drawing, interface details, dimension datums, clocking convention, installed-route evidence, service envelope, quantity and required inspection records. Review available stainless steel braided PTFE hose assembly options, then request project-specific confirmation. Product-page content does not confirm an exact replacement, standard, tolerance, test or delivery scope.
Send the Existing Assembly Evidence and Replacement Requirements
Ready to request a quote? Send your drawing or specifications, quantity, destination country and operating conditions for a project-specific review.

